Lessons in Public Engineering: Inside the 1995 Istanbul M2 Metro Tender Cancellation

Lessons in Public Engineering: Inside the 1995 Istanbul M2 Metro Tender Cancellation

 In 1995, a fresh engineering team at Istanbul Metropolitan Municipality (İBB) stood firm during grueling 7-month contract talks for the M2 Metro Line. Despite pressure from a major Siemens-led consortium, the team refused to compromise on public interest and technical specifications—resulting in the tender’s cancellation and the forfeiture of a $9 million bid bond. Here is the insider account of how engineering ethics shaped Istanbul's transit history.


Introduction: A Turning Point in Taksim

It was during a stressful a-year-and-a-half stretch right after I left Siemens—a period when I was running my own business, trying to stand on my own two feet, and noticing the very first gray hairs appearing on my head.

I want to share the story of liquidating the company I co-founded with partners, transitioning to İstanbul Ulaşım A.Ş., and navigating the lengthy contract negotiations for the 1995 M2 metro line electromechanical systems tender—a major deal awarded to a Siemens-led consortium that ultimately fell through without a signed contract.


The Transition and the Offer

Our company's liquidation process was still underway, though I still went out into the field occasionally to service equipment for a few legacy clients. Around that time, Mr. Mükremin Karaağaç—who had recently stepped into an executive role at the Istanbul Metropolitan Municipality (İBB)—reached out to me.

Knowing my background at Siemens, he told me that the electromechanical tender for the Taksim metro line had been finalized and that a contract would soon be signed. He offered me a position on the newly established project team at İstanbul Ulaşım A.Ş. It was an opportunity I couldn't have asked for.


Executive Interviews and Initial Leadership

To complete the hiring process, I was interviewed by the Head of Municipal Enterprises at İBB, Candan Karlıtekin; that was the first time we ever met. (Interestingly, twelve years later, when I was being appointed as Head of Ground Operations at Turkish Airlines (THY), he was the Chairman of the Board, and we had another interview.)

I also met with Adem Baştürk, the Deputy Secretary General. During the upcoming negotiations, Mr. Baştürk frequently visited the jobsite container offices and chaired our meetings. Around that time, the late Mustafa Açıkalın served as Secretary General and dropped in on our sessions as well.


Building the Team in Jobsite Containers

On paper, I was on the payroll of İstanbul Ulaşım A.Ş. However, specialized municipal units that would later design metro projects or provide engineering consultancy simply didn't exist back then. The organization hadn't accumulated that institutional memory yet.

Our Electromechanical Project Team brought together a diverse group of engineers:

  • Sebahattin Doğan (Project Coordinator & retired Deputy General Manager of SEKA)
  • Çetin Tepehan (Assistant Coordinator)
  • Hakkı Ekşioğlu (International Experience)
  • Hikmet Erçin (Retired from TCDD)
Under the Technical Affairs Directorate beneath the Department of Public Works, Mükremin Bey led the Taksim metro project alongside Site Manager Dursun Balcıoğlu. On site, I joined experienced colleagues Feriha Mert, Şükrü Demircioğlu, and Hasan Sandıkçı (Recep Kırlı also worked with us briefly before moving to İGDAŞ).

We were also joined by eager junior engineers straight out of university, including İsmail Eroğlu (who continues his career in private sector metro projects) and Şükrü İlhan (who later moved to TEK).

We worked side by side out of temporary container offices set up right in Taksim Gezi Park to gain hands-on site experience while tunneling works progressed below us.


The Negotiation Table: Technical vs. Administrative

Three to four times a week, representatives from the Siemens consortium and our municipal technical advisory team sat down for grueling, hours-long contract sessions.

We operated across two dedicated tables:

  1. Administrative & Financial Table
  2. Technical Specifications Table
Leadership wanted these negotiations finalized quickly so we could proceed to signing. Yet, despite rumors years later that the process was "predestined for cancellation," I attended every single meeting from day one to the end—there was never any hidden agenda. We were there to get a fair contract executed.


The Crux of the Dispute: The "LOT" Method

In complex transit systems, international best practice locks down performance requirements (lumens, acoustic decibels, ventilation airflow) and specifies quantities on a LOT (lump-sum team/set) basis.

The LOT method forces contractors to deliver optimized engineering rather than billing by unit count:

  • Contractor A might use high-efficiency technology and satisfy lighting requirements with 80 fixtures.
  • Contractor B might choose cheaper fixtures, requiring 120 units to hit the exact same standard.
Under the tender specification, both bid a lump-sum price for "1 LOT". However, during contract talks, the contractor consortium insisted on adding reservations:

"We based our bid on an estimate of 100 fixtures; if we install more, we expect unit-rate variation payments."

Our engineering team stood firm: the LOT structure embedded in the specifications was non-negotiable.


Administrative Roadblocks and $224 Million

While technical debates were intense, what truly stalled negotiations were the contractor's persistent administrative demands.

Negotiations proceeded based on the $224 million USD tender figure (lowered from an initial $269 million estimate prior to talks). By the sixth month, discussions seemed complete. However, the Siemens consortium repeatedly refused to sign the original specification as written, demanding ongoing administrative concessions.

Later, Siemens representative Karl Neubeck claimed in the press that the municipality had unilaterally altered contract terms. That was a distortion of facts. All bidding firms had accepted the specifications upfront. When İBB in good faith allowed minor adjustments, it opened the gates to relentless demands. When İBB finally put its foot down and demanded adherence to the original terms, the consortium balked.


Cancellation & The $9 Million Forfeiture

Because the consortium refused to execute the contract as specified, İBB formally canceled the tender. As a direct legal result, the consortium’s temporary bid bond of approximately $9 million USD was forfeited and retained by the city.

Following the specification as written would have cost the consortium far more than $9 million, so they chose to absorb the loss.

This outcome reshaped municipal policy forever: İBB completely abolished pre-signature contract negotiations for future projects, establishing a strict rule that winning bidders must sign specifications verbatim.


Final Reflection: Standing on Engineering Integrity

At the time, the tender cancellation felt like a bitter disappointment after seven months of grueling effort. Yet, the stance we took—unwavering commitment to engineering standards and public interest—remains a point of deep professional pride.

Standing up for sound engineering practices and protecting public resources may not always yield a quick signature, but it is the only principled way forward.


Comments

Popular posts from this blog

An Engineer's Career Journey

The Secret Letter of Recommendation My Father Wrote

Against All Odds: How Young Engineers Built Türkiye’s First Domestic Tramway (RTE2000)